| Documents Approved |
|
At the Design Review Board Meeting today at the City of Scottsdale, the Preliminary Documents of our Second Story Addition were approved! This is a great moment as we are now able to proceed at full speed with the Construction Documents, which have already been started. The goal that we have agreed to with our Architect Dan Bedrin is that we are targeting to submit our Construction Documents to the City in 2 to 3 weeks. They should take about 2 weeks to turn around after the City receives the documents.
We are also now in the process of meeting with three (3)
bidders and will provide them with the construction documents at the same time
as we provide them to the city. Upon
City approval (hopefully 4 to 6 weeks from this date of July 10) we will be in
a position to award the Contract to the preferred bidder. Your LWLC Building Committee |